26-03 2024
Shenzhen Shenhui Intercity Dapeng Branch Line five industrial area project Kwai Chung station big mileage section successfully sealed
On March 17, with the completion of the concrete pouring of the last floor, the large mileage section of Kwai Chung Station of the Wugong Area project of Shenhui Intercity Dapeng Branch Line was successfully sealed, achieving another milestone node, providing favorable conditions for the subsequent shield construction. -
19-03 2024
The first floor of the north section of the Haitai Yangtze River Tunnel has been poured
On March 14, after more than 10 hours of pouring operations, the first floor of the north section of the Haitai Yangtze River Tunnel was successfully poured, opening the prelude to the construction of the main structure of the tunnel project. -
06-03 2024
Taizhou Jiefang Road cross-river tunnel has officially entered the physical construction stage
On March 1, the first steel cage of the ground connecting wall of the Jiangbei starting section of Taizhou Jiefang Road Cross-River Tunnel and South Connection Project (Phase I) entered the trough smoothly, marking that the project officially entered the physical construction stage of the project. -
26-02 2024
Xiamen Electric Power and Qingshui Island Tunnel project will be excavated from the coast to the end of the island and is expected to be completed and put into use in 2026
Recently, it was learned that Xiamen's key livelihood project - Xiamen Power and water Island Tunnel project has entered the shield phase of the sea section, the project coastal bottom to the end of the island, is expected to be completed and put into use in October 2026. -
16-01 2024
Hefei Xinqiao Airport Line S1 first shield section double line through
On the morning of January 12, with the breaking of the "Struggle No. 2" shield tunneling machine, the right line of the Guzhen Road Station - shield tunneling section of the advance section of Hefei Xinqiao Airport Line S1 was successfully broken through, marking the first double penetration of the area in the whole line, and the key progress of the project construction. -
19-12 2023
All 6 shield tunneling machines in Hebei section of Beijing Rail Transit Line 22 have been excavated